Construction of the 1000 MW Hydroelectric Power Plant of Gotvand and Blocking of Diversion Tunnel

Project Specifications

Client
The Iran Water & Power Resources Development Company
Consultant
Mahabghodss Consulting Engineering Company
Primary Cost of Project
36 million Dollars
Final Cost of Project
41 million Dollars
Award Date
2004
Date of completion
2013
Duration
102 Month
Excavation
340,000 m3
Reinforcement
16,000 ton
Concrete work
195,000 m3
Formwork
100,000 m2
Heavy steel structure
1,000 ton
Shot Crete
200,000 m2

Energy and Power