Construction of sub crust concerning Lot No.12 of the Bafgh-Bandar Abbas Double Track Railway

Project Specifications

Client
The Ministry of Road and Transportation
Consultant
Iran Oston Consulting Engineering Company
Primary Cost of Project
23 million Dollars
Final Cost of Project
35 million Dollars
Award Date
1980
Date of completion
1987
Duration
81 Month
280 Bridges with Large Spans of up 30 m Wide
Earth Filling
3,300,000 m3
Concrete Work
160,000 m3
Formwork
120,000 m2

Road & Relvant Constructions