Construction of the Second Lot of the Zarrinshahr-Shahrekord-Broojen Main Road

Project Specifications

Client
The Ministry of Road and Transportation
Consultant
Harazrah Consulting Engineering Company
Primary Cost of Project
23.8 million Dollars
Final Cost of Project
55 million Dollars
Award Date
1977
Date of completion
1995
Duration
189 Month
Length of Road
43 km
Length of Bridge
244 m
Height of Pre-Stressed Slab
16 to 25 m
Length of Tunnel
1 km

Road & Relvant Constructions