Part of Civil Works of Golshahr-Hashtgerd Electrical Rail way

Project Specifications

Client
Hashtgerd New Town Company
Consultant
Harazrah Consulting Engineering Company
Primary Cost of Project
18 million Dollars
Final Cost of Project
23 million Dollars
Award Date
2008
Date of completion
2013
Duration
58 Month
Reinforcement
8,000 ton
Concrete work
100,000 m3
Formwork
142,000 m2
Foundation Excavation
300,000 m3
Excavation
700,000 m3
Earth filling
200,000 m3

Road & Relvant Constructions