The second part of the main road leads – Bydlh to BAZOFT ( Karun 4 )

Project Specifications

Client:
The Iran Water & Power Resources Development Company
Consultant:
Rahavar Consulting Engineering Company
Primary Cost of Project:
18.5 million Dollars
Final Cost of Project:
30 million Dollars
Award Date:
2004
Date of completion:
2007
Duration:
41 Month

Road & Relvant Constructions