Water Intake Super Structure of Gotvand Hydroelectric Power Plant

Project Specifications

Client
The Iran Water & Power Resources Development Company
Consultant
Mahabghodss Consulting Engineering Company
Primary Cost of Project
35 million Dollars
Final Cost of Project
42.7 million Dollars
Award Date
2009
Date of completion
2011
Duration
34 Month
No. of cylindrical shaft
4
Height of shaft
70 m
Diameter of shaft
13 m
Reinforcement
12,500 ton
Concrete work
190,000 m3
Formwork
90,000 m2
Steel structure
95 ton